Capital Improvement Plan 2016
 

Capital Improvement Plan 2016

The Board of Squaw Valley Mutual Water Company has laid out a 20 year Capital Improvement Plan to address all the outstanding issue with our delivery infrastructure, and keep it operating well into the future. These projects (and their timing) include

PROJECTED TOTAL CIP PROJECT COST
CAPITAL IMPROVEMENT DESCRIPTION BUDGET COST PLAN YEAR
1 Complete 2015 Back Lot Main Abandonments $12,300 2016
2 Pothole, Locate and ID Main Well 1 to Squaw Valley Rd $9,400 2017
3 Horizontal Well Investigation $14,900 2018
4 Horizontal Well Rehab, Pipe/Valve Replacement $54,800 2018
5 East Christy Main Replacement/Looping Main $350,500 2016-2017
6 Replace Sandy/Lanny Interconnect Piping $178,600 2023-2024
7 PSD-MWC Intertie $57,000 2022
8 West End Main Replacement Ph 1: Christy Lane $132,200 2027-2028
9 West End Main Replacement Ph 2: Washoe Dr/Paiute Pl $338,200 2031-2032
10 West End Main Replacement Ph 3: Navajo Ct $167,500 2025-2026
11 West Sandy Main Replacement $492,200 2034-2035
12 Well Trans Main Ph 1: Well 1 to Squaw Valley Rd $225,000
13 Well Trans Main Ph 2: Well 2 to Well 1 $81,400
14 Well Trans Main Ph 3: Sandy to Storage Tank $197,600
ESTIMATED TOTAL CIP $2,311,600

These projects are paid for, except for the last 4,  from a $75,000 annual investment in Capital Infrastructure Improvements reserve. The Board will continually update the plan, evaluating actual vs budgeted costs, and create alternatives for addressing the last 4 items.

 

Billing Questions?

Office Manager, Daniel Collin

Phone: (530) 583-3674

Fax: (530) 583-0677

Email: Send A Message 

PO Box 2276,

Olympic Valley, CA 96146


 

Pay Your Water Bill Here:

Enter Your Sequence Id

Service Questions?

Maintenance & Operations

Squaw Valley Public Service District

PO Box 2026

Olympic Valley, CA 96146

Phone: (530) 583-4692

Sign up for e-mail notification

  • Send us your comments